2022 03 10

The Via Vika project – behind the scenes on the first use of closed cavity façades in Northern Europe

Share case study:

The Via Vika building in Oslo, Norway, is a ground-breaking project for many reasons. It is the first ever building in Northern and Eastern Europe to feature a closed cavity façade (CCF). It also combines two different types of façade – CCF and single skin (SSF). Then there is the sheer scale of the project – the 20 000 m² office and retail complex features over 2,000 façade units. 

Staticus designed, manufactured and installed the façade for the Via Vika project, using ingenuity, teamwork and expertise to overcome challenges at every stage. These included:

  • Designing and installing a solution that featured different types of both façade – closed cavity and single skin,
  • Working with complex materials including patterned stainless steel coated in Rosy Gold via a deposition process, and natural limestone,
  • Realising a bold architectural vision that included two separate buildings and a skylight 12m in diameter,
  • Creating completely new production facilities in order to produce CCF façade elements using Dry Air technology for the first time ever, 
  • Undertaking the company’s largest ever façade installation, which was interrupted by quarantines due to the COVID-19 pandemic.

In this case study we will look behind the scenes at how the Staticus team completed this ambitious and complex project.

3 major innovations during the concept design phase

The concept design phase of the Via Vika project lasted more than 2 and a half years. And a number of challenges were solved during this period, from the façade types themselves, through to materials and design of the skylight.


Challenge 1: Façade types

By far the most significant task during the concept development phase was to design a system built on two types of façade – single skin and closed cavity. 

The decision to include closed cavity façades in the project was a bold one. No building in Northern or Eastern Europe had such façades, and it was not a requirement of the project to include them.

But Staticus’ façade engineers quickly understood that using CCF would bring a number of advantages. It would help them to tackle one of the project’s biggest technical challenges – how to have blinds that could be easily maintained on the external façade. Here is Giedrius Valantinas, Project Manager for the Via Vika project, to explain more.

There were requirements to have blinds on the external facade, and to have easy maintenance and cleaning of those blinds. This meant a double skin façade was the best option. So we quickly saw that CCF would solve this problem, along with bringing many other advantages. The maintenance is easier because you only need to clean 2 surfaces, external and internal. Whereas when you have a standard double-skin facade, you need to clean 4 surfaces – you need to open the window from the inside (which disturbs those who are working and is difficult because of tables and other furniture), then clean both sides of the windows.

Giedrius ValantinasProject Director

Using closed cavity façades also brought a range of other performance benefits. The CCF units designed by the Staticus team offer very good thermal insulation (0.54 W/m2K). They also give excellent sound insulation.
As a result of the decision to use CCF, the team had to devise a solution incorporating two façade types.

By having two façade types, we could address different requirements of the building. For the external envelope, which requires higher levels of sound reduction and is more exposed to the sun, we could use closed cavity. While the inner façade can be single skin as it is less exposed to external noise levels and also has a different visual look, as intended by the architects.

Giedrius ValantinasProject Director

The final proposal put forward by Staticus, based on closed cavity and single skin façades was selected for the project because it was the best fit for the project’s performance requirements. 

Challenge 2: The materials

For the cladding, the original proposal was to use copper for its visual effect. However, previous research and tests by the Staticus team indicated that there are higher levels of pollution from using copper, and this pollution gets into a city’s water management system. That is because when it rains the copper ionizes (this is due to acidity in the rain itself). 

So instead, the designers proposed using stainless steel coated with titanium coating. This achieves a similar visual effect to copper, but at a lower cost to the environment. Plus it will keep the same visual appearance for its entire lifetime. 

Along with stainless steel, the project also included working with natural limestone, which also meant the cladding needed to be carefully planned at the preproduction stage.

Challenge 3: The skylight

The Via Vika project design included one very adventurous feature – a skylight 12 meters in diameter built into the ground level on the pavement between the two buildings. 

The effect for visitors is stunning. Travelling on escalators below the skylight, the effect for visitors is akin to being in the bottom of a canyon. The two Via Vika buildings loom over them as they slowly ascend.

But achieving this effect presented a significant design challenge. In the end, the Staticus design team created a solution utilising 12-metre steel beams and huge horizontal glass panels that are 6 metres in length and 3 metres in width. 

Proceeding to mock-ups and testing 

With the design concept approved, the next step was to develop mock-ups and carry out testing on the façade elements. 

The Via Vika project team worked together with the RnD, Quality, and Installation departments at Staticus to develop mock-ups of both the closed cavity and single skin façades that would be used in the project. 

A series of tests were run in Staticus’ own facility and the mock-ups were approved by the client. They were then un-mounted and shipped to the IFT Rosenheim international test center in Germany. The tests included:

  • Water and air permeability testing,
  • Wind resistance testing. 

Both façade systems withstood water shot as 1,200Pa and 600Pa from a grid of high-pressure nozzles placed in front of them.

With testing complete and the client’s approval already given, it was time for the production of the more than 2,000 elements needed. 

Read more
All resources
2024 03 28
2 façade innovations, 1 goal – improved sustainability in the façade industry
Read more
2024 02 07
Staticus continues to evolve with a focused and ambitious strategy for 2024-27
Read more
2024 03 04
Health & Safety at work reporting brings clarity and results at Staticus
Read more
2023 10 12
“Making sure our goals align” – reflections on the Wates’ Supplier Conference 2023
Read more
2023 07 13
Carbon and costs in context: insights from High-Rise Northern Exposure
Read more
2023 07 03
Staticus’ own aluminium façade system based on DfM successfully tested and ready for production
Read more
2023 06 21
Staticus’ next generation Hybrid Unitised Façade used for first time in Textiltorget project, Sweden
Read more